NotesQuantitative AptitudeArithmetic
Time & Work
Notes
In this topic
Starts from the school method (one day's work is 1/10), shows why days never add, and replaces it with the LCM method: take the total work as the LCM of the days, so each person's speed is a whole number of units a day. Then works a question where one worker leaves partway.
Focused Aspirant
The rest of the notes
Key points and What to expect for Time & Work, with every video, past paper and mock.
Unlock with Focused AspirantLoading the rest of the notes…
The full notes
Every idea from zero, worked examples step by step, the question types the exam asks, and practice.
Read the Time & Work notesTest yourself
Tap an option to answer. The first tap counts.
- Q1Easy
Anil can paint a fence in 10 hours, and Bina can paint the same fence in 15 hours. How long will they take to paint it working together?
Correct answer6 hours
Why
Add rates, never times: in 30 hours Anil would paint 3 fences and Bina 2.
Together they paint 5 fences in 30 hours, so one fence takes hours.
They take 6 hours.
- Q2Easy
Priya is twice as efficient as Rahul. Working together, they finish a project report in 12 days. How many days would Rahul take to finish it alone?
Correct answer36
Why
Twice as efficient means Priya does 2 units a day for Rahul's 1, so the pair does 3.
In 12 days that is 36 units, the whole report.
Rahul alone, at 1 unit a day, takes 36 days.
8 more questions: 1 easy, 4 medium, 3 hard
Sign in free to see the rest and get your score.